NSW Planning Guide

How NSW Planning Proposals Work: Pre-Exhibition to Made

Process guide · 8 min read

A planning proposal in NSW is the formal mechanism for amending a Local Environmental Plan (LEP) — the instrument that controls what can be built on land, how tall, and how dense. Unlike a development application (DA), which seeks approval for a specific building, a planning proposal changes the rules themselves. If it succeeds, the land is permanently rezoned.

Planning proposals are processed under the Environmental Planning and Assessment Act 1979 (EP&A Act), primarily Part 3. Every planning proposal in NSW follows a defined lifecycle, and understanding each stage tells you exactly what's happening — and what comes next.

The planning proposal lifecycle

Stage 1

Pre-Exhibition

A proposal starts with the planning proposal authority — normally the council, which is the body that prepares and submits it. A landowner or developer can ask the council to do so, and usually does the work, but the council is the one that lodges. The council forms its own view first, then submits the proposal to the Department for a gateway determination. At this point it is recorded on the NSW Planning Portal but not yet exhibited, which makes it the earliest public signal that a site's development potential may be changing.

Stage 2

Under Assessment

The Department of Planning is reviewing the proposal at the gateway stage. DPHI assesses strategic consistency with State and regional plans, infrastructure capacity, and site-specific merit. This stage can range from weeks to several months depending on the complexity of the proposal and departmental workload.

Stage 3

Gateway determination

The gateway determination is the formal decision on whether the proposal may proceed to public exhibition. It is made by the Minister for Planning, in practice through the Department under delegation — not by the council, which cannot determine its own proposal. It may be unconditional, conditional on specific studies, or refused. This is a milestone rather than a phase: what takes the time is satisfying the conditions that come with it. See our gateway determination guide.

Stage 4

On Exhibition

The proposal is open for public comment, for a period the gateway determination sets. Twenty-eight days is the common fallback rather than a floor written into the Act — the gateway can require longer, and for some low-impact proposals shorter or none at all. Community members, government agencies, and affected landowners can make written submissions. This is when the proposal becomes fully public — and when it typically attracts the most attention in the market.

Stage 5

Post-Exhibition

Council reviews all submissions received during exhibition and prepares a post-exhibition report. Where significant issues were raised — traffic, heritage, environmental constraints — additional studies or design changes may be required before the proposal can advance. This is where many proposals stall for extended periods, sometimes years.

Stage 6

Finalisation

Council has resolved to support the proposal and is forwarding it to the Department for making. The formal LEP amendment instrument is being legally drafted and checked for consistency. This is typically the last milestone before the rezoning takes effect. Proposals at Finalisation have a very high probability of being Made.

Stage 7 — Final Outcome

Made

The LEP amendment has been gazetted. The rezoning is legally effective. The land's planning controls — zone classification, height of buildings (HOB), floor space ratio (FSR) — have permanently changed. This is the endpoint every proponent is working towards.

Alternative Outcomes

Withdrawn / Not Proceeding

Withdrawn: The proponent has pulled the proposal. Can happen at any stage — most commonly Pre-Exhibition (before significant costs are sunk) or Post-Exhibition (if the post-exhibition report is unfavourable). Not Proceeding: Council has resolved not to proceed with the proposal, or DPHI has refused at gateway or post-exhibition. Both outcomes end the proposal's lifecycle without a rezoning.

How long does the process take?

We are not going to give you a median, because NSW does not publish what it would need to be measured from. A planning proposal has no published lodgement date, and the exhibition start and end dates are empty on every one of the 5,027 proposals on record. Any "typical time to Made" you read — ours included, until today — is an estimate dressed as a measurement.

What the record does support: 3,964 of those 5,027 proposals have been Made. Proposals commonly run for years rather than months, and the long pole is almost always satisfying gateway conditions rather than the assessment itself.

Timelines vary significantly by proposal type, council, and the number of gateway conditions imposed. The biggest delays occur at Post-Exhibition — particularly when agency consultation is unresolved or additional environmental studies are required. Proposals with clean strategic alignment and minimal environmental constraints move substantially faster.

Who submits planning proposals?

Planning proposals vs development applications

A common source of confusion. A planning proposal changes the rules that apply to land — it amends the LEP. A development application (DA) seeks approval for a specific project under the existing rules. The planning proposal comes first; the DA comes after, once the land has been rezoned. Some development bypasses the DA pathway entirely through the complying development certificate (CDC) route — the low-rise pattern book designs under Chapter 7 of SEPP (Housing) 2021 are the clearest example.

Why tracking planning proposals matters

A proposal detected at Pre-Exhibition represents an early signal that a site's development potential may be about to change significantly — often before the land value has adjusted to reflect that possibility. By the time a proposal reaches Exhibition, it's well-known. By the time it's Made, the opportunity has largely been priced in.

The intelligence advantage is in the early stages: Pre-Exhibition, gateway determination, and the Post-Exhibition stalls that indicate where the process is running into problems — and potentially where a proponent might need to sell.