How Long Does a DA Take in NSW?

Data guide · 6 min read

The honest answer is that it depends enormously on which council you lodge with — far more than most people expect. We measured every development application determined across New South Wales in the last twelve months.

56 days Median time from lodgement to determination for a development application in NSW, measured across 40,828 determined applications in the last twelve months.

That single figure hides the thing that actually matters: the council. In the slowest it is 118 days, for the same kind of application.

Why the "average DA time" you read elsewhere is usually wrong

Most published figures mix every kind of application together, and that produces a number that describes a council's workload mix rather than its speed.

Application typeMedianDetermined in 12 months
Development Application56 days40,828
Complying Development Certificate4 days37,164
Modification Application37 days12,444
All types combined28 days94,333

A Complying Development Certificate is determined in a median of 4 days because it is a compliance check against fixed standards, not a merit assessment. A real development application takes 56. A council that processes a lot of CDCs will therefore post an excellent combined figure while its DAs take just as long as anyone else's.

This is why the combined number is misleading. Across NSW the all-types median is 28 days. For actual development applications it is 56. If you are comparing councils, compare like with like — every figure on this page is development applications only.

How long a DA takes, by council

Councils with at least 50 determined development applications in the last twelve months, so the median means something. 110 of the 128 NSW councils clear that bar.

Slowest

CouncilRegionMedianDetermined
Liverpool City CouncilGreater Sydney118 days475
Warrumbungle Shire CouncilCentral West and Orana101 days77
Hunters Hill CouncilGreater Sydney100 days110
Yass Valley CouncilSouth East and Tablelands99 days255
Gunnedah Shire CouncilNew England North West98 days88
Tweed Shire CouncilNorth Coast97 days629
Sutherland Shire CouncilGreater Sydney92 days646
Ku-ring-gai CouncilGreater Sydney90 days366
Woollahra Municipal CouncilGreater Sydney88 days406
Cumberland City CouncilGreater Sydney88 days520
City of RydeGreater Sydney88 days243

Source: NSW Planning Portal, determined development applications in the last twelve months, measured by Lodgd. Median is the middle value — half of applications were faster, half slower. Councils with fewer than 50 determinations are excluded because a median over a handful of applications is noise rather than a pattern.

What actually drives the difference

A slow median is not automatically a badly run council, and a fast one is not automatically efficient. The things that move the number:

The practical use of the number is comparison, not judgement: if you are choosing between sites in two council areas, a 120-day difference in the median is a real difference in holding costs.

The statutory clock is not the same as the real one

New South Wales sets assessment periods after which an applicant may treat an application as refused and appeal — the "deemed refusal" period. That period is a right to appeal, not a deadline the council must meet, and the figures above show how far the two diverge in practice. Most applicants wait rather than appeal, because appealing restarts the process somewhere more expensive.