Every development application and planning proposal lodged with Ku-ring-gai Council, tracked daily from the NSW Planning Portal — and what share of it actually gets built.

Ku-ring-gai Council determines a development application in a median of 90 days34 days slower than the NSW median of 56.

Measured across 364 determined development applications, last 12 months · 8,741 applications on record · 75 planning proposals · 126,324 people · 41,864 dwellings

Housing approved since 1 July 2024 · updated 15 Sept 2026

2,119 homes have been approved here

Counted from 1,747 of 1,986 determined applications — the ones stating a number of new homes, which for many of them is zero. The other 239 leave the field blank, and blank is not a zero. Applicants recorded 2,139; 20 homes are not counted here, from 19 applications whose own figures cannot be true.

198 still to be decided · 9% · 323 homesUnder assessment 192 · Under appeal 61,832 determined · 85% · 1,939 homes119 withdrawn or stopped · 6% · 207 homesWithdrawn 118 · Not proceeding 1

323 homes are still waiting on a decision. This is every application lodged since 1 July 2024 and where it stands today — the homes figure beside it covers applications determined in the same period, which is a different set.

What kind of housing

Apartments and shop-top leads what Ku-ring-gai Council has approved

Apartments and shop-top1,041
Dwelling house779
Multi-dwelling and terraces90
Seniors and specialised housing79
Dual occupancy78
Secondary dwelling35

3 smaller categories are not shown. An application can carry more than one type, so these do not sum to the total above.

NSW’s housing target

NSW asks Ku-ring-gai Council for 7,600 homes by June 2029

That target counts homes finished; everything above counts applications. A home can be approved and never built, and NSW measures the target against ABS completions data that Lodgd does not hold. The two are not a percentage of one another.

Approved is not built

Across NSW, only 50% of approved homes reach construction within two years.

An approval is not a house. Lodgd matches every application to the construction certificates that follow it, site by site, across all 128 councils — so the pipeline can be read as what is likely to exist rather than what was lodged.

Register your interest →

Measured over 247,565 homes approved in the last 24 months.

Latest activity

Updated every morning from the NSW Planning Portal

  • Lodged59 RIDGE STREET GORDON 207214 Sept 2026
  • Lodged9 BALMARINGA AVENUE SOUTH TURRAMURRA 207414 Sept 2026
  • Lodged37 TURRAMURRA AVENUE TURRAMURRA 207414 Sept 2026
  • Lodged11 HUNTER AVENUE ST IVES 207511 Sept 2026
  • Lodged161 FOX VALLEY ROAD WAHROONGA 207611 Sept 2026
  • ProposalKu-ring-gai Local Environmental Plan 2015 - 47 Warrane Road, Roseville Chase — Not Proceeding1 May 2026
  • ProposalKu-ring-gai Local Environmental Plan 2015 - 69 Kissing Point Road, Turramurra — Withdrawn1 May 2026

Elsewhere in NSW

Every council, the same way

How we count. These figures count homes written on development applications and complying development certificates lodged with Ku-ring-gai Council and published on the NSW Planning Portal. NSW’s Housing Supply Dashboard counts something different. Across NSW the two land within 6% of each other; council by council they differ by more than 20% about half the time, and in both directions — for some councils NSW’s figure is far higher, for others far lower. Ours is checked application by application against the Planning Portal itself, and matches it exactly in every council tested. Lodgd publishes what is in the applications, and says so rather than adjusting to match.