NSW · Central West and Orana · Regional

Lithgow City Council

An approval is not a home. Lodgd follows every application in Lithgow City Council through to what gets built.

Lithgow City Council determines a development application in a median of 91 days — 35 days slower than the NSW median of 56.

Measured across 129 determined development applications, last 12 months · 1,600 applications on record · 10 planning proposals · 20,693 people (2025 ABS estimate) · 8,319 occupied dwellings (2021 Census)

Housing determined since 1 July 2024

170 homes have been determined here

Counted from the applications that state a number of new homes. Where an application does not state one, it is not read as a zero. A home decided twice at the same address is counted once.

NSW’s housing target

Lithgow City Council has no council-level target.

Outside the four target areas. Covered by the single 55,000-home regional NSW allocation, which NSW does not break down by council.

Approved is not built

Across NSW, only 57% of homes determined reach construction within two years.

Lodgd matches every application to the construction certificates that follow it, site by site, across all 128 councils — so the pipeline can be read as what is likely to exist rather than what was lodged.

Try the free demo →

Measured over 193,554 homes determined between July 2021 and November 2024 — every decision old enough to have had two full years to start.

Of every hundred homes NSW determines, this many have a construction certificate — building work can legally begin — within two full years.

Latest activity

Straight from the NSW Planning Portal

  • DA1399 GLEN DAVIS ROAD CAPERTEE 2846Lodged30 Oct 2026
  • CDC8 BURNETT STREET WALLERAWANG 2845Lodged26 Oct 2026
  • CDC5 GIRRAWEEN DRIVE MARRANGAROO 2790Lodged26 Oct 2026
  • CDC527 GREAT WESTERN HIGHWAY MARRANGAROO 2790Lodged23 Oct 2026
  • DA54 BARTON STREET LITHGOW 2790Lodged22 Oct 2026
  • Planning proposalLithgow Local Environmental Plan 2014: Housekeeping AmendmentsFinalisation26 Mar 2025
  • Planning proposalLithgow LEP 2014 - Amendment 6 - Additional Permitted Use LidsdaleMade25 Apr 2022

Elsewhere in NSW

Every council, the same way

How the system works. What happens to a DA · How long they take · Complying development vs a DA · All guides →

How we count. These figures count the homes stated on development applications and complying development certificates lodged with Lithgow City Council, checked against the NSW Planning Portal. Where another source counts differently, Lodgd publishes what is in the applications rather than adjusting to match.