NSW · Greater Sydney · Urban

City of Parramatta Council

Every development application and planning proposal lodged with City of Parramatta Council, tracked daily from the NSW Planning Portal — and what share of it actually gets built.

City of Parramatta Council determines a development application in a median of 83 days27 days slower than the NSW median of 56.

Measured across 429 determined development applications, last 12 months · 14,671 applications on record · 139 planning proposals · 273,106 people · 92,109 dwellings

Housing approved since 1 July 2024 · updated 15 Sept 2026

4,804 homes have been approved here

Counted from 2,543 of 3,172 determined applications — the ones stating a number of new homes, which for many of them is zero. The other 629 leave the field blank, and blank is not a zero. Applicants recorded 5,280; 476 homes are not counted here, from 32 applications whose own figures cannot be true.

271 still to be decided · 8% · 603 homes2,903 determined · 89% · 2,674 homes107 withdrawn or stopped · 3% · 41 homesWithdrawn 105 · Not proceeding 2

603 homes are still waiting on a decision. This is every application lodged since 1 July 2024 and where it stands today — the homes figure beside it covers applications determined in the same period, which is a different set.

What kind of housing

Apartments and shop-top leads what City of Parramatta Council has approved

Apartments and shop-top2,300
Dual occupancy730
Dwelling house581
Multi-dwelling and terraces482
Residential (form not stated)440
Secondary dwelling236

8 smaller categories are not shown. An application can carry more than one type, so these do not sum to the total above.

NSW’s housing target

NSW asks City of Parramatta Council for 19,500 homes by June 2029

That target counts homes finished; everything above counts applications. A home can be approved and never built, and NSW measures the target against ABS completions data that Lodgd does not hold. The two are not a percentage of one another.

Approved is not built

Across NSW, only 50% of approved homes reach construction within two years.

An approval is not a house. Lodgd matches every application to the construction certificates that follow it, site by site, across all 128 councils — so the pipeline can be read as what is likely to exist rather than what was lodged.

Register your interest →

Measured over 247,565 homes approved in the last 24 months.

Latest activity

Updated every morning from the NSW Planning Portal

  • Lodged24 BARCLAY ROAD NORTH ROCKS 215114 Sept 2026
  • Lodged1 WENTWORTH STREET PARRAMATTA 215014 Sept 2026
  • Lodged5 WOODBERRY ROAD WINSTON HILLS 215314 Sept 2026
  • Lodged63 STIRLING AVENUE NORTH ROCKS 215114 Sept 2026
  • Lodged35 MACQUARIE STREET PARRAMATTA 215014 Sept 2026
  • ProposalPlanning Proposal for land at 6 Hope St, Melrose Park (Goodman site) — Under Assessment9 July 2026
  • Proposal135 George Street and 118 Harris Street, Parramatta (the Albion Hotel) (291 dwellings and 82 jobs) — Withdrawn1 May 2026

Elsewhere in NSW

Every council, the same way

How we count. These figures count homes written on development applications and complying development certificates lodged with City of Parramatta Council and published on the NSW Planning Portal. NSW’s Housing Supply Dashboard counts something different. Across NSW the two land within 6% of each other; council by council they differ by more than 20% about half the time, and in both directions — for some councils NSW’s figure is far higher, for others far lower. Ours is checked application by application against the Planning Portal itself, and matches it exactly in every council tested. Lodgd publishes what is in the applications, and says so rather than adjusting to match.