Blue Mountains City Council

Every development application and planning proposal lodged with Blue Mountains City Council, tracked daily from the NSW Planning Portal — and what share of it actually gets built.

Blue Mountains City Council determines a development application in a median of 71 days15 days slower than the NSW median of 56.

Measured across 484 determined development applications, last 12 months · 5,583 applications on record · 29 planning proposals · 78,876 people · 30,528 dwellings

Housing approved since 1 July 2024 · updated 15 Sept 2026

572 homes have been approved here

Counted from 771 of 1,197 determined applications — the ones stating a number of new homes, which for many of them is zero. The other 426 leave the field blank, and blank is not a zero. Applicants recorded 575; 3 homes are not counted here, from 3 applications whose own figures cannot be true.

167 still to be decided · 12% · 161 homesAwaiting lodgement 1 · Under assessment 1661,095 determined · 81% · 488 homes97 withdrawn or stopped · 7% · 43 homesWithdrawn 82 · Not proceeding 15

161 homes are still waiting on a decision. This is every application lodged since 1 July 2024 and where it stands today — the homes figure beside it covers applications determined in the same period, which is a different set.

What kind of housing

Dwelling house leads what Blue Mountains City Council has approved

Dwelling house389
Secondary dwelling83
Apartments and shop-top26
Dual occupancy23
Multi-dwelling and terraces17
Demolition10

4 smaller categories are not shown. An application can carry more than one type, so these do not sum to the total above.

NSW’s housing target

NSW asks Blue Mountains City Council for 600 homes by June 2029

That target counts homes finished; everything above counts applications. A home can be approved and never built, and NSW measures the target against ABS completions data that Lodgd does not hold. The two are not a percentage of one another.

Approved is not built

Across NSW, only 50% of approved homes reach construction within two years.

An approval is not a house. Lodgd matches every application to the construction certificates that follow it, site by site, across all 128 councils — so the pipeline can be read as what is likely to exist rather than what was lodged.

Register your interest →

Measured over 247,565 homes approved in the last 24 months.

Latest activity

Updated every morning from the NSW Planning Portal

  • Lodged29 HILL STREET WENTWORTH FALLS 278211 Sept 2026
  • Lodged48 PRITCHARD STREET WENTWORTH FALLS 278211 Sept 2026
  • Lodged21-23 KINGS ROAD LEURA 278011 Sept 2026
  • Lodged9 BARINGA STREET BLAXLAND 277410 Sept 2026
  • Lodged2 VICTORIA STREET KATOOMBA 278010 Sept 2026
  • ProposalAmendment 25 to Blue Mountains LEP 2015 (Leuralla Amphitheatre and Dam Sites) — On Exhibition14 July 2026
  • ProposalAmendment 13 (clause 1.9 low rise code exemption) — Not Proceeding1 May 2026

Elsewhere in NSW

Every council, the same way

How we count. These figures count homes written on development applications and complying development certificates lodged with Blue Mountains City Council and published on the NSW Planning Portal. NSW’s Housing Supply Dashboard counts something different. Across NSW the two land within 6% of each other; council by council they differ by more than 20% about half the time, and in both directions — for some councils NSW’s figure is far higher, for others far lower. Ours is checked application by application against the Planning Portal itself, and matches it exactly in every council tested. Lodgd publishes what is in the applications, and says so rather than adjusting to match.